Monday, October 18, 2010

Construction on40-turbine wind project

Bangor Daily News:
"The Lincoln Planning Board approved the project on Dec. 1, 2008, with the other host towns eventually following suit. The Maine Department of Environmental Protection’s permit for the First Wind subsidiary came in April 2009, but the project, probably the most protested since wind-to-energy companies began investing in Maine, had been in civil court since then.

The Friends of Lincoln Lakes, a citizens group formed to oppose the project, took its series of appeals to the Maine Supreme Judicial Court but lost. Its latest appeal, to the Board of Environmental Protection on Oct. 7, was rejected."

No comments: