Friday, October 16, 2009

Kibby Ridge to StartUp

The Boston Globe:
"The ceremony will mark the completion of the first 22 windmills and the start of their production of power, which will flow to Central Maine Power Co. and through its interconnections to the New England grid.

The second 22 windmills in the project, on Kibby Ridge, are scheduled for completion in late summer or early fall of next year, said Corey Goulet, vice president of energy projects for TransCanada. The portion of the project to be dedicated today will provide the equivalent average energy needs of 25,000 homes.

When all 44 windmills are completed, the Kibby Mountain windmills will provide twice that power and become New England’s largest wind power project. It has an overall cost of $320 million, said Goulet."